Planning Applications & Appeals Details

This page displays details of the current application selected.

To view the location of this site on the map press the Webmap button below.

You can view the architects drawings submitted as part of a planning application, prior to the application being determined at Live Applications

The Notification of a Decision on any Planning application will be issued by post to the applicant via their agent (where applicable) as soon as possible after the decision is made.

A copy of that Decision Notice (for all notices issued from 15 March 2010) will be available for public viewing from the link shown at the bottom of this page on the day following posting. Any Conditions and/or reasons attached to the decision will be included in that notification.


The Important Dates section the 'End of Consultation Date' will alter as the application proceeds and will normally change to reflect the end date of the 21 day site notice consultation period once the site notice has been erected by the applicant/agent and the confirmation slip is received by the Planning Service.

NOTE: Please do not use the 'End of Consultation Date' under the Important Dates section on this screen for the date Representations need to be submitted to the Planning Service.

The date Representations are required back to the Planning Service are listed under the individual Applications - Please look for the Application at Live Applications

Information provided by this service is updated overnight at the end of each day.

Application Progress
ReceivedValidConsultation CommencedSite AssessmentDecision Notification
 
 
 
 
 
 
     

Application Details
Application Number   FULL/2017/2398 
Site AddressCentral Stores
Guernsey Electricity
North Side
Vale
Guernsey 
Application Type   Ordinary Application 
Applicant Name   Guernsey Electricity 
Development Description   Install photovoltaic array to 4 south facing roofslopes.  
Current Status / Decision   Notification of Grant of Full Planning Permission. 
Agent    Guernsey Electricity 

Important Dates
Received Date   22/09/2017 
Valid Application Received Date   22/09/2017 
Start of Consultation Date   06/10/2017 
End of Consultation Date   30/10/2017 
Decision Notification Date   03/11/2017 

 

Site Visits
Site Visit Dates   04/10/2017